File #: 16-347    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 8/17/2016 In control: Council
On agenda: 8/22/2016 Final action: 8/22/2016
Title: Public Safety Building Apparatus Bay Extension Contract Award
REQUEST FOR DECISION

DATE: August 17, 2016 Report No. FIRE-16-004
TO: Laurie Hurst, Chief Administrative Officer
FROM: Chris Jancowski, Fire Chief
SUBJECT:

Title
Public Safety Building Apparatus Bay Extension Contract Award
End

RECOMMENDATION:

Recommendation
1. That Council award the Contract for construction to Saywell Contracting Limited.
2. That Council assign $438,900 from the Capital Project Reserve Fund for the construction of the Public Safety Building Apparatus Bay Extension.
Body

RELEVANT POLICY:

N/A

STRATEGIC RELEVANCE:

Well Managed and Well Maintained Infrastructure
Esquimalt Town Square Development


BACKGROUND:

The Public Safety Building Apparatus Bay Extension Project will consist of an addition in order to extend the current apparatus bays. This project will allow the relocation of the current apparatus and equipment located within the blue building. The blue building is scheduled to be removed as soon as possible to facilitate the development of the Esquimalt Town Square (ETS).

Core work for the project includes:
* Excavation of the parking lot area to allow for servicing of utilities and footings
* Removal and replacement of drainage, garden beds and parking lot surfaces
* Construction of approximately 106 sq. meters of floor space with walls and roof
* Installation of electrical, mechanical and building systems
* Relocation and addition of apparatus bay doors
* Modification and relocation of apparatus exhaust systems
* Connection of exterior finishes into the existing building
* Repair to existing sidewalks
The tender for the project was released on July 19, 2016 and closed on August 05, 2016. The preferred completion schedule for this project was identified to be October 31, 2016. Evaluation criterion for this project was based on cost, schedule, experience and past performance.

A total of three bids were received:
Century Group Inc. Constructors.
* $395,850.00
* 56 Days
Saywell Contracting Ltd.
* $399,000.00
* 45 Days
...