PERIOD REPORT

DATE: May 28, 2018 Report No. EPW-18-022
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:TITLEEngineering and Public Works - 2018 First Period Report

Body
The following is a report on the activities pertaining to the Engineering and Public Works from January 1, 2018 to April 30, 2018.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewer
* 8 service laterals installed (new) this period (total for the year = 8).
* 8 service laterals replaced (due to blockages) this period (total for the year = 8).
* Test and clear inspections as and when required.
* 0 manholes replaced this period (total for the year = 0).

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Preparing annual program for pump maintenance/controls inspection.
* Program also includes coordinating similar activities for View Royal pump stations.
* Initial work for developing scope of work for lockout locations on the various stations has been completed. Work to be carried out in the second period of 2018.

3. Storm Drains
* 8 service laterals installed (new) this period (total for the year = 8).
* 6 service laterals replaced (due to blockages) this period (total for the year = 6)
* Test and clear inspections as and when required.
* 2 manholes replaced this period (total for the year = 2).
* Program for catch basin cleaning was initiated. Spot cleaning ongoing for the remainder of the year.
* Training program for spill response has been passed back to the Township from the CRD. Working with other stakeholders to develop a scope for the program.

4. Liquid Waste Management
Waste Water - inflow and Infiltration
* Strategy for cost sharing was presented to Committee of the Whole in the third period.
* Staff to develop feedback into a working strategy in 2018.
* The Engineering Department to begin modeling the sanitary sewer system in the first per...