Title: Engineering and Public Works - 2017 First Period Report
PERIOD REPORT

DATE: May 8, 2017 Report No. EPW-17-018
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:TITLEEngineering and Public Works - 2017 First Period Report
Body
The following is a report on the activities pertaining to the Engineering and Public Works from January 1, 2017 to April 30, 2017.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewers
* 7 service laterals installed/replaced this period (total for the year = 7).
* Test and clear inspection as and when required.
* 1 manhole replaced this period (total for the year = 1).

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Preparing annual maintenance program for pump maintenance and controls inspection.
* Program also includes coordinating similar activities for View Royal pump stations.
* Developing scope of work for Seahaven pump station valve replacement.
* Developing scope of work for lockout locations on the various stations.

3. Storm Drains
* 3 service laterals installed/replaced this period (total for the year = 3)
* Test and clear inspections as and when required.
* 0 manholes replaced this period (total for the year = 0).
* Program for catch basin cleaning was initiated. Work to be done in the second period.
* Working with CRD and other municipalities to develop a joint training program for spill response training.

4. Waste Management
Waste Water - inflow and Infiltration
* Staff is working on development of the parameters of the approved strategy with a report being prepared in the second period of 2017.
* A Request for Proposal for modeling of the sanitary collection system is to be released and interpretation of smoke testing results to take place in the second period of 2017.
Liquid Waste Management Plan
* Working with CRD/Project Board/Contractor staff on review of traffic management plan.
Integrated Watershed Management
* Staff participating as a mem...