PERIOD REPORT

 

DATE:                       May 9, 2016                     Report No. EPW-16-014

TO:                       Laurie Hurst, Chief Administrative Officer                                           

FROM:                      Jeff Miller, Director of Engineering and Public Works

SUBJECT:TITLE Engineering and Public Works - 2016 First Period ReportBody

 

The following is a report on the activities pertaining to the Engineering and Public Works from January 1, 2016 to April 30, 2016.

 

I.                     DIVISION ACHIEVEMENTS AND ACTIVITIES

 

1.                     Sanitary Sewers

                     9 service lateral installed/replaced this period (total for the year = 9)

                     0 test and clear inspection has been carried out for this period (total for the year = 0)

                     0 manholes replaced this period (total for the year = 0)

 

2.                     Pump Stations

                     Crews have been carrying out routine maintenance activities.

                     Preparing request for quotation for annual maintenance program that will include pump maintenance and controls inspection.

                     Uganda pump station suffered a catastrophic power failure. Crews maintained pump station operation with portable generator while power supply was repaired.

 

3.                     Storm Drains

                     5 service lateral installed/replaced this period (total for the year = 5)

                     0 test and clear inspection has been carried out for this period (total for the year = 0)

                     0 manhole replaced this period (total for the year = 0)

 

4.                     Manhole Separation

                     Funds allocated to 2015 Manhole Separation Program to be utilized on a case by case basis due to complexity of manhole separation. This work will be carried out in 2016 and beyond.

                     A total of 78 manholes were separated over the five year program.

                     Remaining combined manholes is 42

                     18 end of pipe

                     21 within easements on private property

                     3 not on easements on private property

 

5.                     Waste Management

 

Waste Water - inflow and Infiltration

                     Staff is working on the development of the parameters of the approved strategy.

                     In the second period, a request for proposal for modeling of the sanitary collection system is to be released.

                     Interpretation of smoke testing results to take place in the second period.

 

Liquid Waste Management Plan

                     Staff participated on the development of various aspects of a sub-regional treatment system both through Westside Solutions and the CRD.

                     Staff has participated on the communication, technical and administrator committees.

 

Integrated Watershed Management

                     CRD working on common design guidelines for storm water management in a phased stage approach. Staff participating as a member of the committee.

 

6.                     Roads

                     Pothole repair being carried out as required.

                     Spring clean has been carried out.

                     Crack sealing program is scheduled to begin in early part of the second period. Supplies have been ordered.

                     Carried out surface restoration for third parties.

                     Approximately 112 tonnes of asphalt placed for the period (total for the year = 112 tonnes)

 

7.                     Traffic Management

                     Preliminary preparation work was initiated on the traffic count analysis and various other studies for potential corridor modification.

 

8.                     Sidewalks - Maintenance

                     Carried out surface restoration for third parties.

                     Approximately 56 cubic meters of concrete (includes curb and gutter and sidewalk panels) was placed (total for the year = 56 cubic meters)

                     Approximately 226 linear meters was replaced for the period (total for the year = 226 linear meters)

 

9.                     Sidewalk Ramps

                     Two sidewalk ramps will be installed this year under the capital program.

                     The locations of the ramps are being determined.

 

10.                     Trip Hazards

                     As per Council Policy PLAN-17 Sidewalk Maintenace, trip hazard inspection survey has been completed.

                     Survey determined that there are:

§                     28 - No. 1 trip hazards

§                     81 - No. 2 trip hazards

§                     153 - No. 3 trip hazards

                     Work will begin in the second period for correction of the hazards.

 

11.                     Regional Transportation Plan

                     The Township is waiting on the CRD to begin discussions on the Regional Transportation Plan.

 

12.                     Bus Shelters

                     Normal maintenance schedule underway.

                     Includes refuse collection, graffiti removal and power washing of the shelters and sidewalks adjacent to them.

 

13.                     Solid Waste Management

 

Garbage and Kitchen Scraps Collection

                     Operations normal

                     Number of additional garbage and organic bins purchased to the end of period = 12 (total additional bins purchased since 2014 = 132)

                     Tonnage of garbage waste stream collected for period = 333.17 (total for the year = 333.17)

                     Tonnage of kitchen scraps collected for period = 167.36 (total for the year = 167.36)

                     Total Tonnage for year = 500.53 (total for same period 2015 = 489.68)

                     CRD is continuing the program processing of kitchen scraps in out of region locations.

                     The CRD will be looking at the possibility of combining kitchen scraps, bio solids and yard/garden waste. No schedule has been communicated to the Township for this.

                     It is expected that tipping fee for kitchen scraps will increase from $110 per tonne to $120 per tonne in 2017.

 

Yard and Garden

                     Operations normal

                     Usage of transfer station during period: January to March

o                     Esquimalt residents = 4,041 (total for the year = 4,041).

o                     View Royal residents = 1,562 (total for the year = 1,562).

o                     Commercial = 85 (total for the year = 85).

o                     Tonnage removed from site = 363.77 (total for the year = 363.77).

o                     Tonnage removed in 2015 first period = 369.94 (total for 2015 = 2188.75).

                     Contract is in the last six months of life. Working with Town of View Royal onto determine look of new contract.

 

Recycling

                     Operations normal

 

14.                     Fleet

                     Operations normal

                     Fleet purchase for 2016 has begun. Units to be purchased:

o                     Concrete mixer

o                     1 ton service truck

o                     Command unit

o                     Van

o                     Crew cab with dump box

                     Beginning update on Fleet Plan.

 

15.                     Work for Others

                     Work orders for call outs and/or repairs at View Royal pump stations for the period = 2 (total for the year = 2).

                     Work orders issued for asphalt/sidewalk repairs following work by other utilities for the period = 17 (total for the year = 17).

                     Work orders issued for sanitary and storm services to accommodate new development in the period = 4 (total for the year = 4)

 

16.                     Capital Projects

 

16.1                     Traffic Counts

                     Traffic counts for road network were carried out at the end and beginning of first and second periods.

                     Preparing a request for proposals for analysis of this data plus previous data for interpretation of traffic movements in the second period.

 

16.2                     Lampson Street Corridor Cross Section Study

                     Study to be carried out to determine corridor’s ability to accept bike lanes in order to increase its multi modal orientation.

                     Preparing a request for proposals in second period.

 

16.3                     Tillicum Street Corridor Study

                     Study to be carried out to determine the impact of the addition of a signalized intersection between Gorge Park and Craigflower Road on traffic movements.

                     Preparing a request for proposals in the second period.

 

16.4                     Lyall Street Corridor Study

                     The study will look at the corridor’s cross section to determine if it should be modified and how.

                     Preparing a request for proposals in the second period.

 

16.5                     Review of Public Works Fuel Tanks

                     The study will review the integrity of the fuel tanks at Public Works and confirm the condition that of the tanks.

                     Preparing a request for proposals in the second period.

 

16.6                     Inspection of Masonry Structures

                     An inventory of the masonry structures has been completed.

                     In the second period a consultant will be retained to assist in the assessment of the structures.

 

16.7                     Municipal Hall Upgrade

                     The flooring in the Municipal Hall requires upgrading due to its age and usage.

                     In addition the common areas of the Hall require painting.

                     Preparing a request for quotation for the second/third period.

 

16.8                     Replacement of Emergency Generator at Public Works

                     This project will upgrade the emergency generator to ensure that the public works operations and secondary emergency operations centre will not be impeded by a lack of power.

                     A tender will be issued in second/third period.

 

16.9                     Colville/Hutchinson Intersection Upgrade

                     This project will see the intersection of Colville and Hutchinson upgraded to facilitate pedestrian movements and bus stop shelters.

                     Design work was initiated in 2015 with work to be carried out in the first half of 2016.

 

16.10                     Esquimalt Road and Lampson Road Intersection Upgrade

                     This project will undertake the upgrade of the existing infrastructure for the signalized intersection and remove the Township’s dependency on the usage of BC Hydro poles.

                     Design of the upgrade has been completed and the project will go out for tender in conjunction with the Old Esquimalt and Lampson Road Intersection Upgrade project.

                     A tender will be issued for the work in the first half of 2016.

 

16.11                     Old Esquimalt and Lampson Intersection Upgrade

                     The intersection will be refitted with new light infrastructure and light sequence.

                     The design and construction is anticipated to be completed in conjunction with the Esquimalt Road and Lampson Street intersection.

 

16.12                     Admirals Road Corridor

                     Surface works were completed in 2015.

                     Remaining work is the installation of LED streetlights that will occur in the second/third period.

 

16.13                     Catch Basin Replacement

                     This is the last year of a three year program.

                     The program will replace catch basins that have come to the end of their operational life.

                     The new catch basins will meet today’s standards to assist in the control of sediment to receiving bodies.

                     There are a total of 60 catch basins that are included in the program.

                     41 catch basins have been replaced in the last two years.

                     It is anticipated that 20 catch basins will be replaced in 2016.

                     There were 14 catch basins replaced in this period (a total of 14 this year).

 

16.14                     Sidewalk Capital Program

                     This project increases the sidewalk network in length and improves connectivity.

                     The program will see the installation of a concrete sidewalk between Esquimalt Road and Old Esquimalt Road (832 Esquimalt Road).

                     Design will occur in second period, construction in second/third period.

 

16.15                     Sidewalk Replacement Program

                     This project sees existing sidewalks upgraded to current standards.

                     Head Street (east side) from Dunsmuir Road to Wollaston Street will be constructed in the second period.

 

16.16                     Road Capital Program

                     Council approved $50,000 for additional works on asphalt surfaces.

                     Staff determining locations for Capital Road Maintenance and Project funding.

                     Work to be carried out in the second/third period.

 

16.17                     Concrete Capital Program

                     Council approved $50,000 for additional works on concrete surfaces.

                     One site has been chosen to improve access and trip hazard remediation.

                     Sites have been evaluated and work to be carried out in conjunction with the Colville/Hutchinson Intersection Upgrade Project in 2016.

 

16.18 Esquimalt Road Improvements

                     Council approved funding for asphalt and concrete removal and replacement. This work will occur in the second period.

                     Funding was approved for curb paint removal along with weed control. This work will occur early in the second period.

 

16.19                     ETAG

                     Work continues as required.

 

16.20                     Esquimalt Village Project Advancement

 

Brown Field Remediation

                     A fifth round of drilling was carried out in the first period.

                     This work was carried out to assist with the delineation of contamination boundaries.

                     Working with consultant to finalize remediation strategy and obtain Ministry of Environment acceptance.

 

16.21                     Public Works HVAC

                     Work is scheduled for late second period/early third period.

 

16.22                     Public Works Card Access System

                     Work is scheduled for late second period/early third period.

                     Preliminary design to start in second period.

 

16.23                     Municipal Hall Stairwell Leak

                     In the second period, work will start on preliminary scope of work and tender package.

 

17.                     Traffic Orders

                     Number of traffic orders issued this period = 3 (total for the year = 3)

 

18.                     Development Applications

                     Number of development applications for engineering comments this period = 9 (total for the year = 9)

                     Number of building permit applications for engineering comments = 25 (total for the year = 25)

 

II.                     COMMITTEES

 

                     No staff is appointed to sit on any Council appointed committees.