PERIOD REPORT

DATE: May 9, 2016 Report No. EPW-16-014
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:TITLE Engineering and Public Works - 2016 First Period ReportBody

The following is a report on the activities pertaining to the Engineering and Public Works from January 1, 2016 to April 30, 2016.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewers
* 9 service lateral installed/replaced this period (total for the year = 9)
* 0 test and clear inspection has been carried out for this period (total for the year = 0)
* 0 manholes replaced this period (total for the year = 0)

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Preparing request for quotation for annual maintenance program that will include pump maintenance and controls inspection.
* Uganda pump station suffered a catastrophic power failure. Crews maintained pump station operation with portable generator while power supply was repaired.

3. Storm Drains
* 5 service lateral installed/replaced this period (total for the year = 5)
* 0 test and clear inspection has been carried out for this period (total for the year = 0)
* 0 manhole replaced this period (total for the year = 0)

4. Manhole Separation
* Funds allocated to 2015 Manhole Separation Program to be utilized on a case by case basis due to complexity of manhole separation. This work will be carried out in 2016 and beyond.
* A total of 78 manholes were separated over the five year program.
* Remaining combined manholes is 42
* 18 end of pipe
* 21 within easements on private property
* 3 not on easements on private property

5. Waste Management

Waste Water - inflow and Infiltration
* Staff is working on the development of the parameters of the approved strategy.
* In the second period, a request for proposal for modeling of the sanitary collection system is to be released.
* Interpretation of smoke testin...