File #: 19-423    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 9/9/2019 In control: Committee of the Whole
On agenda: 9/16/2019 Final action: 9/16/2019
Title: Integrated Resource Management
Attachments: 1. Attachment No. 1 - RFP ENG 19-10 IRM Consultant
REQUEST FOR DIRECTION

DATE: September 11, 2019 Report No. EPW-19-032
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:

Title
Integrated Resource Management
End

ESSENTIAL QUESTION:

Does Council want to proceed with the study for the Integrated Resource Management philosophy for solid waste, kitchen scraps, yard/ garden, and sanitary waste latent heat streams?

RECOMMENDATION:

Recommendation
That the COTW receive Staff Report EPW-19-032 for information, provide any additional direction to staff as the COTW considers advisable, and direct staff to prepare a report for Council's consideration.
Body

BACKGROUND:

In February of 2018, a Notice of Motion was introduced to Council for the Township to investigate the possibility that an Integrated Resource Management philosophy be reviewed for the various waste streams produced by the Township. Gasification technology was the preferred process for the treatment of several of the streams.

This subject was further discussed at the March 2018 Committee of the Whole. The Committee provided direction to staff that a line item be part of the budget discussions for the 2019-2023 Financial Plan. In May of 2019, this project was approved with a budget of $75,000 assigned to it.

During discussions, the Capital Regional District [CRD] continued work treatment processes for both the bio solids waste stream and kitchen scraps waste stream. For the bio solids, anaerobic technology was chosen to treat the bio solids. Disposal of the treated bio solids is a subject still under discussion.

A request for proposal was issued for the treatment of the kitchen scraps in late 2018/early 2019. No decision has been made on the treatment methodology or how to deal with the end product(s) and staff have not been updated on the status of this project.

ISSUES:

Staff has prepared a Request for Proposal for the study of IRM philosophy with respect to the Township...