On agenda: 2/26/2018 Final action: 2/26/2018
Title: Amendment to Development Permit DP000077, Core Area Waste Water Treatment Plant - 337 Victoria View Road
Attachments: 1. Appendix A -DP000077 Amendment, 2. Appendix B - Context Map, 3. Appendix C - Architect’s Narrative DP000077 Amendment, 4. Appendix D - Mcloughlin Point Design Guidelines
REQUEST FOR DECISION

DATE: February 20, 2018 Report No. DEV-18-010
TO: Laurie Hurst, Chief Administrative Officer
FROM: Bill Brown, Director of Development Services
SUBJECT:

Title
Amendment to Development Permit DP000077, Core Area Waste Water Treatment Plant - 337 Victoria View Road
End

RECOMMENDATION:

Recommendation
That Council approve the amendments to Development Permit DP000077 [Appendix "A"] for Core Area Waste Water Treatment Plant, 337 Victoria View Road, (PID 030-006-813) Lot 1, Section 11, and part of Bed of Victoria Harbour Esquimalt District Plan EPP36468 [Appendix "B"], as attached to Staff Report DEV-18-010.
Body

RELEVANT POLICY:

- Official Community Plan Bylaw, 2006, No. 2646
- Zoning Bylaw, 1992, No 2050
- Parking Bylaw, 1992, No. 2011
- Development Application Procedures and Fees Bylaw, 2012, No. 2791
- Advisory Planning Commission Bylaw, 2012, No. 2792
- Subdivision and Development Control Bylaw, 1997, No. 2175
- Host Community Impact 5-Year Agreement
- Community Impact Mitigation & Operating Agreement
- Amenity Reserve Fund Administration Agreement
- Statutory Right of Way for future public trail


STRATEGIC RELEVANCE:

The proposed development permit is not directly related to any of Council's strategic priorities in the 2015 - 2019 Strategic Plan

BACKGROUND:

Through the iterative design process, several modifications to the approved design have occurred resulting in changes to the form and character of the original approved development. (The revised drawings are attached as a schedule to the Amending Development Permit attached as Appendix "A" to this report). These changes include:

- Removal of some of the building mass at the south end of the building;
- A slight increase in the height of the second floor of the Operations and Maintenance building;
- Removal of the translucent panels from the upper east side of the treatment plan building;
- The addition of translucent panels to the odour control room;
- Changing the...