The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 19-020    Version: 1 Name:
Type: Period Report Status: Engineering and Public Works Staff Report
File created: 1/3/2019 In control: Special Committee of the Whole
On agenda: 1/14/2019 Final action:
Title: Engineering & Public Works - 2018 Third Period Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PERIOD REPORT

DATE: January 14, 2019 Report No. EPW-19-001
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering & Public Works
SUBJECT:TITLE Engineering & Public Works - 2018 Third Period Report
Body

The following is a report on the activities pertaining to the Engineering & Public Works from September 1, 2018 to December 31, 2018.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewer
* 2 service laterals installed (new) this period (total for the year = 12).
* 6 service laterals replaced (due to blockages) this period (total for the year = 21).
* Test and clear inspections as and when required.
* 0 manholes replaced this period (total for the year = 0).

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Annual program for pump maintenance/controls inspection has been completed.
* Program also includes coordinating similar activities for View Royal pump stations.
* Scope of work for lockout locations on the various stations has been completed. Work to be initiated upon approval of Financial Plan.

3. Storm Drains
* 3 service lateral installed (new) this period (total for the year = 18)
* 2 service laterals replaced (due to blockages) this period (total for the year = 11).
* Test and clear inspections as and when required.
* 0 manhole replaced this period (total for the year = 3).
* 5 catch basins replaced this period (total for the year = 5).
* 1 new catch basin installed this period (total for the year = 1).
* Program for catch basin cleaning was completed. Spot cleaning ongoing for the remainder of the year.
* Completed grant application for end of pipe treatment structures for Gorge Creek and West Bay collection basins and submitted to Infrastructure Canada; we are waiting for a response.

4. Liquid Waste Management

Waste Water - Inflow and Infiltration
* Continuing to develop a cost sharing strategy and bylaw for inflow and infiltration mitigatio...