File #: 24-431    Version: 1 Name:
Type: Staff Report Status: Agenda Ready
File created: 9/11/2024 In control: Council
On agenda: 9/23/2024 Final action:
Title: Engineering & Public Works Departments - 2024 Second Period Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PERIOD REPORT

DATE: September 23, 2024 Report No. EPW-24-022
TO: Dan Horan, Chief Administrative Officer
FROM: Joel Clary, Director of Engineering & Public Works
SUBJECT:TITLEEngineering & Public Works Departments - 2024 Second Period Report
Body

The following is a report on the activities pertaining to the Engineering & Public Works Departments from May 1, 2024 to August 31, 2024.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewer
* 5 new service laterals installed this period (7 total for the year).
* 10 service laterals replaced (due to blockages) this period (18 total for the year).
* Test and clear inspections as and when required.
* 2 new manholes installed this period (2 total for the year).

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Annual pump maintenance/controls inspections of kiosks completed in the second period. Pump inspections to be completed in the third period of 2024.
* Program also includes coordinating similar activities for View Royal pump stations.
* No overflow events to report in the second period.

3. Storm Drains
* 2 new service laterals installed this period (4 total for the year).
* 2 service laterals replaced (due to blockages) this period (9 total for the year).
* Test and clear inspections as and when required.
* 2 new manholes installed this period (3 total for the year).
* 0 catch basins replaced this period (0 total for the year).
* 3 new catch basins installed this period (3 total for the year).
* Program for catch basin cleaning expected in the third period.

4. Liquid Waste Management Plan
* Participated on the Esquimalt Liaison Committee, with a meeting in May. CRD continues to receive and investigate odour complaints.
* Participated in initial discussions with the CRD led Core Area Liquid Waste Management Plan Technical Working Group to review an update to the Core Area Liquid Waste Management Plan in 2022. Minimal discussions in 2023. Wo...

Click here for full text