PERIOD REPORT
DATE: May 25, 2026 Report No. EPW-26-003
TO: Dan Horan, Chief Administrative Officer
FROM: Joel Clary, Director of Engineering & Public Works
SUBJECT:TITLEEngineering & Public Works Departments - 2026 First Period Report
Body
The following is a report on the activities pertaining to the Engineering & Public Works Departments from January 1, 2026 to April 30, 2026.
I. DIVISION ACHIEVEMENTS AND ACTIVITIES
1. Sanitary Sewer
* 4 new service laterals installed this period (4 total for the year).
* 10 service laterals replaced (due to blockages) this period (10 total for the year).
* Test and clear inspections as and when required.
* 1 new manhole installed this period (1 total for the year).
2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Annual pump maintenance/controls inspections of kiosks to be completed in the second period.
* Program also includes coordinating similar activities for View Royal pump stations.
* 0 overflow events occurred in the first period (0 total for the year).
3. Storm Drains
* 4 new service laterals installed this period (4 total for the year).
* 4 service laterals replaced (due to blockages) this period (4 total for the year).
* Test and clear inspections as and when required.
* 0 new manholes installed this period (0 total for the year).
* 1 catch basin replaced this period (1 total for the year).
* 0 new catch basins installed this period (0 total for the year).
4. Liquid Waste Management Plan
* Participated on the Esquimalt Liaison Committee with community group representatives and CRD staff regarding the Sewer Treatment Plant. There are now two meetings per year, along with two email updates by the CRD. The 2026 meetings are in March and September. CRD continues to receive and investigate odour complaints.
* CRD completing update to the I&I section of the Core Area Liquid Waste Management Plan with ongoing work by CRD continuing throughout 2026.
...
Click here for full text