The livestream of the meeting can be viewed on most devices. If you are using Chrome and are unable to view the meeting, please use an alternate web browser such as Firefox or Microsoft Edge. Should you experience other technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 16-025    Version: 1 Name:
Type: Staff Report Status: Filed
File created: 1/6/2016 In control: Committee of the Whole
On agenda: 1/11/2016 Final action: 1/11/2016
Title: Engineering and Public Works - 2015 Third Period Report
Attachments: 1. Staff Report EPW-16-005
PERIOD REPORT

DATE: January 11, 2016 Report No. EPW-16-005
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:TITLE Engineering and Public Works - 2015 Third Period ReportBody

The following is a report on the activities pertaining to the Engineering and Public Works Department from September 1, 2015 to December 31, 2015.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewers
* 8 service lateral installed/replaced this period (total for the year = 22)
* 1 test and clear inspection been carried out this period (total for the year = 4)
* 1 manholes replaced this period (total for the year = 2)

2. Pump Stations
* Crews have been carrying out routine maintenance activities
* Annual maintenance program has been carried out. Actions recommended in the maintenance report have been completed.
* Work to replace the internal piping at the Kinver and Sea Haven pump stations has been completed.

3. Storm Drains
* 7 service lateral installed/replaced this period (total for the year = 19)
* 1 test and clear inspection carried out for this period (total for the year = 3)
* 1 manhole replaced this period (total for the year = 2)
* Replacement of catch basins is being carried out under capital program.
* Catch basin inspections increased during the fall to keep them clear during increased storm events.
* There were three reported spill incidents during this period.

4. Manhole Separation
* Completion of the 2014 program occurred in the second period.
* Work has been initiated on the 2015 work program and will be completed in the first half of 2016.
* Number of manholes separated this period 0 (total for the year = 7). All together there were 12 manholes separated in 2015. This total includes the five manholes included in the Admirals Road Project.

5. Waste Management
Waste Water - inflow and Infiltration
* Staff completed developing an I/I stra...