The livestream of the meeting can be viewed on most devices. If you are using Chrome and are unable to view the meeting, please use an alternate web browser such as Firefox or Microsoft Edge. Should you experience other technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 21-645    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 12/15/2021 In control: Council
On agenda: 12/20/2021 Final action: 12/20/2021
Title: Shallow Utility Line Installation/Potential Pathway Along Devonshire Road Between Lampson Street and Fairview Road
REQUEST FOR DECISION

DATE: December 15, 2021 Report No. 2021-21-031
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:

Title
Shallow Utility Line Installation/Potential Pathway Along Devonshire Road Between Lampson Street and Fairview Road
End

RECOMMENDATION:

Recommendation
That Council receive this report for information.
Body

RELEVANT POLICY:

Sidewalk Master Plan
Pedestrian Charter

STRATEGIC RELEVANCE:

Local Services and Infrastructure
* Identify infrastructure repair and proactively plan for replacement needs
* Identify long term financial requirements for local services and infrastructure


BACKGROUND:

Shaw Cablesystems Ltd (Shaw) began their design of a shallow utility line along Devonshire Road between Lampson Road to Fairview Road in December 2020. An initial submission for municipal approval was made in February of 2021 which required revision due to conflicts with existing lines and a change in scope by Shaw. The second submission was received and approved in September of 2021. Construction occurred in November/December of 2021. The following are the features of the project:

* Located along south side of Devonshire Road
* Located behind curb for majority of the way except in front of a portion of 769 Lampson Road and all of 929 Devonshire Road
* Boulevard from Lampson to Porter is grassed with driveways
* Boulevard from Porter to Fairview is grassed with driveways
* Trench width to be a minimum of 450 mm to maximum of 600 mm
* Trench depth to be approximately 1,000 mm deep with straight cut walls
* Trench backfill was granular in nature due to removal of native material during construction
* Restoration to match existing conditions of surface features
o Approximately surface width restoration 600 mm
o Surface restoration included grassed boulevard and driveway crossings


ISSUES:

1. Rationale for Selected Option

Council has received a concern that this cons...