Legislation Details

File #: 26-367    Version: 1 Name:
Type: Staff Report Status: Agenda Ready
File created: 11/3/2026 In control: Council
On agenda: 11/16/2026 Final action:
Title: Gosper Sewer Upgrades - Construction Contract Award, Staff Report No. EPW-26-016
Attachments: 1. Attachment 1 - Gosper Sewer Upgrades - Design Drawings
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TOWNSHIP OF ESQUIMALT STAFF REPORT
MEETING DATE: November 16, 2026 Report No. EPW-26-016

TO: Council
FROM: Charles Davie, Manager of Engineering
SUBJECT: Gosper Sewer Upgrades – Construction Contract Award

RECOMMENDATION:

Recommendation
That Council award construction contract ENG 26-04, including optional work and future change orders within the approved budget, to Alterra Construction Ltd. in the amount of $351,747, excluding GST, for Gosper Sewers Upgrades, as described in staff report EPW-26-016.
Body

EXECUTIVE SUMMARY:

The purpose of this report is to award a construction contract for the replacement of aging sanitary and storm sewer mains on Gosper Crescent. The work involves pipe bursting of a sanitary and storm sewer main, each approximately 127 metres in length, associated service reconnections, drainage improvements and surface restoration.

BACKGROUND:

The Township's sanitary and storm sewer networks contain aging infrastructure that requires replacement to maintain service reliability and reduce the risk of failures. The existing sanitary and storm sewer mains along Gosper Crescent consist of approximately 127 metres each of vitrified clay pipe. These mains have been identified for replacement due to their age and condition. To address these concerns, the Township retained McElhanney Ltd. to complete the detailed design, tender preparation and construction administration for the replacement of both mains.

The proposed works involve replacing the sanitary and storm main with new 200 mm diameter high-density polyethylene (HDPE) pipe using pipe bursting. Pipe bursting involves pulling a new pipe through the alignment of the existing sewer main while breaking apart and displacing the existing pipe. This method reduces the amount of excavation required compared to conventional open-cut construction, limiting impacts to the roadway, driveways and surrounding properties. The project also includes reconnecting existing sanitary and storm se...