The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 16-198    Version: 1 Name:
Type: Staff Report Status: Filed
File created: 5/3/2016 In control: Special Committee of the Whole
On agenda: 5/9/2016 Final action: 5/9/2016
Title: Engineering and Public Works - 2016 First Period Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PERIOD REPORT

DATE: May 9, 2016 Report No. EPW-16-014
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering and Public Works
SUBJECT:TITLE Engineering and Public Works - 2016 First Period ReportBody

The following is a report on the activities pertaining to the Engineering and Public Works from January 1, 2016 to April 30, 2016.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewers
* 9 service lateral installed/replaced this period (total for the year = 9)
* 0 test and clear inspection has been carried out for this period (total for the year = 0)
* 0 manholes replaced this period (total for the year = 0)

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Preparing request for quotation for annual maintenance program that will include pump maintenance and controls inspection.
* Uganda pump station suffered a catastrophic power failure. Crews maintained pump station operation with portable generator while power supply was repaired.

3. Storm Drains
* 5 service lateral installed/replaced this period (total for the year = 5)
* 0 test and clear inspection has been carried out for this period (total for the year = 0)
* 0 manhole replaced this period (total for the year = 0)

4. Manhole Separation
* Funds allocated to 2015 Manhole Separation Program to be utilized on a case by case basis due to complexity of manhole separation. This work will be carried out in 2016 and beyond.
* A total of 78 manholes were separated over the five year program.
* Remaining combined manholes is 42
* 18 end of pipe
* 21 within easements on private property
* 3 not on easements on private property

5. Waste Management

Waste Water - inflow and Infiltration
* Staff is working on the development of the parameters of the approved strategy.
* In the second period, a request for proposal for modeling of the sanitary collection system is to be released.
* Interpretation of smoke testin...