Skip to main content

The livestream of the meeting can be viewed on most devices. If you are using Chrome and are unable to view the meeting, please use an alternate web browser such as Firefox or Microsoft Edge. Should you experience other technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 25-342    Version: 1 Name:
Type: Period Report Status: Agenda Ready
File created: 9/17/2025 In control: Special Committee of the Whole
On agenda: 9/29/2025 Final action:
Title: Engineering & Public Works Departments - 2025 Second Period Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PERIOD REPORT

DATE: September 29, 2025 Report No. EPW-25-015
TO: Dan Horan, Chief Administrative Officer
FROM: Joel Clary, Director of Engineering & Public Works
SUBJECT:TITLEEngineering & Public Works Departments - 2025 Second Period Report
Body

The following is a report on the activities pertaining to the Engineering & Public Works Departments from May 1, 2025 to August 31, 2025.

I. DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewer
* 2 new service laterals installed this period (11 total for the year).
* 5 service laterals replaced (due to blockages) this period (21 total for the year).
* Test and clear inspections as and when required.
* 1 new manhole installed this period (1 total for the year).

2. Pump Stations
* Crews have been carrying out routine maintenance activities.
* Annual pump maintenance/controls inspections of kiosks to be completed in the second period.
* Program also includes coordinating similar activities for View Royal pump stations.
* No overflow events to report in the first period.

3. Storm Drains
* 3 new service laterals installed this period (5 total for the year).
* 2 service laterals replaced (due to blockages) this period (8 total for the year).
* Test and clear inspections as and when required.
* 0 new manholes installed this period (0 total for the year).
* 7 catch basins replaced this period (7 total for the year).
* 1 catch basin repaired this period (1 total for the year).
* 1 new catch basins installed this period (1 total for the year).

4. Liquid Waste Management Plan
* Participated on the Esquimalt Liaison Committee. There are now two meetings per year, along with two updates by the CRD. 2025 meetings are in February and September. CRD continues to receive and investigate odour complaints.
* CRD completing update to the I&I section of the Core Area Liquid Waste Management Plan with ongoing work by CRD expected to progress throughout 2025.
* Reallocation of 0.07 ML/day of al...

Click here for full text