The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 17-138    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 3/28/2017 In control: Council
On agenda: 4/3/2017 Final action: 4/3/2017
Title: Capital Budget Request - Sewer Drain Replacements
REQUEST FOR DECISION

DATE: April 3, 2017 Report No. EPW-17-008
TO: Laurie Hurst, Chief Administrative Officer
FROM: Will Wieler, A/Director of Engineering and Public Works
SUBJECT:

Title
Capital Budget Request - Sewer Drain Replacements
End

RECOMMENDATION:

Recommendation
That Council gives budget approval for Projects 1, 2, 3, & 4 in the amount of $159,000 in the 2017-2021 Financial Plan, as set out in Staff Report EPW-17-008.
Body

RELEVANT POLICY:

Not applicable.

STRATEGIC RELEVANCE:

Well Managed and Maintained Infrastructure - Identify infrastructure repair and proactively plan for replacement needs.

BACKGROUND:

The Township's Engineering and Public Works staff are working on comprehensive infrastructure plans to meet the strategic priorities set out by Council. This is a substantial undertaking that will bring a tremendous benefit to the Township as a whole. In the transition period between now and when the plans are in full motion, the Township still has to address the infrastructure needs as they arise. This past winter season put a significant strain on the sewer and drain infrastructure, and we experienced greater frequency of blockages. In some instances, a need to replace portions of the main lines was identified in order to ensure the continued functionality of the system. The required capital projects would be as follows:

Project 1 - McNaughton Avenue Drain Replacement
* 50 lineal meters of the existing drain main is in need of replacement
* Cost estimate is $25,000

Project 2 - 800 Block Esquimalt Road Sewer Main
* 60 lineal meters of the sewer main is in immediate need of replacement
* Cost estimate for the works is $24,000

Project 3 - 700 Block Lampson Street Sewer Main Replacement
* 120 lineal meters of the sewer main is in immediate need of replacement
* Cost estimate is $65,000

Project 4 - Lockley Road & Intervale Avenue Sewer Drain and Concrete Works
* $50,000 was initially allocated to this project
* Sewer and Drain re...