The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 19-419    Version: 1 Name:
Type: Period Report Status: Agenda Ready
File created: 9/9/2019 In control: Special Committee of the Whole
On agenda: 9/16/2019 Final action:
Title: Engineering & Public Works Department - 2019 Second Period Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PERIOD REPORT

DATE: September 11, 2019 Report No. EPW-19-031
TO: Laurie Hurst, Chief Administrative Officer
FROM: Jeff Miller, Director of Engineering & Public Works
SUBJECT:TITLE Engineering & Public Works Department - 2019 Second Period Report
Body

The following is a report on the activities pertaining to the Engineering & Public Works Department from May 1, 2019 to August 31, 2019.

* DIVISION ACHIEVEMENTS AND ACTIVITIES

1. Sanitary Sewer
* 3 service lateral installed (new) this period (7 total for the year)
* 3 service laterals replaced (due to blockages) this period (13 total for the year)
* Tested and cleared inspections as required
* 0 manholes replaced this period (total for the year = 0)
* 0 new manholes installed this period (total for the year = 0)

2. Pump Stations
* Crews carried out routine maintenance activities
* Annual program for pump maintenance/controls inspections to be carried out in the third period
* Program also included coordinating similar activities for View Royal pump stations
* Scope of work for lockout locations on the various stations completed with tasks to be completed out in the third period

3. Storm Drains
* 3 new service laterals installed (7 total for the year)
* 1 service lateral replaced due to blockages (6 total for the year)
* 1 storm main drain replaced due to failure (1 total for the year)
* Test and clear inspections as required
* 0 manholes replaced (0 total for the year)
* 0 new manhole installed (1 total for the year)
* 0 catch basins replaced (0 total for the year)
* 0 new catch basin installed (0 total for the year)
* Program for catch basin cleaning completed with ongoing spot cleaning
* Discussions with DND and Coast Guard were initiated regarding spill response and some minor joint exercises completed
* Discussions with Public Works Canada will occur in the third period
* Staff will review Infrastructure Canada Grant Program for end of pipe treatment structures for Gorge Creek and West Bay collectio...