The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 17-051    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 1/30/2017 In control: Council
On agenda: 2/6/2017 Final action: 2/6/2017
Title: Early Budget Approval Request
REQUEST FOR DECISION

DATE: January 31, 2017 Report No. P&R-17-002
TO: Laurie Hurst, Chief Administrative Officer
FROM: Scott Hartman, Director of Parks and Recreation Services
SUBJECT:

Title
Early Budget Approval Request
End

RECOMMENDATION:

Recommendation
That Council award early budget approval of $24,000 for two new pool pumps and $18,000 for a replacement pool filter within the 2017-2021 Financial Plan.
Body

RELEVANT POLICY:

Financial Plan 2017-2021

STRATEGIC RELEVANCE:

Council's Operational Strategies 2015-2019 identifies the repair, replacement and upgrades of parks and recreation infrastructure as a strategic priority.

BACKGROUND:

The annual budget schedule allows for budget adoption in May. In order to facilitate the repair of pool equipment during the scheduled annual maintenance shutdown in June 2017 the replacement equipment will need to be ordered and received prior to the May adoption deadline.

ISSUES:

1. Rationale for Selected Option
The replacement of two pool pumps and one pool filter require early budget approval in order to ensure that their installation can be completed during the planned seasonal shut down in June. To ensure that this equipment is on site and ready for installation in June, the order must be placed before the corporate budget is officially approved in May.

2. Organizational Implications
Departmental work plans have been adjusted to include the work associated with this decision.

3. Financial Implications
The $24,000 for the two pool pumps and the $18,000 for the pool filter would appear as one time supplemental items within the 2017-2021 Financial Plan and would be funded through property taxation.

4. Sustainability & Environmental Implications
There are no sustainability or environmental implications associated with this decision.

5. Communication & Engagement
There are no communication or engagement requirements associated with this decision.

ALTERNATIVES:

1) That Counci...