The livestream of the meeting can be viewed on most devices. Should you experience technical difficulties, please review the troubleshooting guide for assistance. If the issue persists, please inform corporate.services@esquimalt.ca and we can relay the information to the webcast support company for assistance. Please note that staff technical support is not available outside of regular business hours or during meetings.

File #: 17-056    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 2/1/2017 In control: Council
On agenda: 2/6/2017 Final action: 2/6/2017
Title: Early Budget Approval for Esquimalt Town Square - Site Development

REQUEST FOR DECISION

 

DATE:                       February 6, 2017                     Report No. EPW-17-004

TO:                       Laurie Hurst, Chief Administrative Officer                                           

FROM:                      Jeff Miller, Director of Engineering and Public Works

SUBJECT:

 

Title

Early Budget Approval for Esquimalt Town Square - Site Development

End

 

RECOMMENDATION:

 

Recommendation

That Council gives early budget approval for inclusion in the 2017-2021 Financial Plan of Project 1 in the amount of $579,000, Project 2 in the amount of $100,000, and Project 3 in the amount of $212,000, for Esquimalt Town Square Site Development as set out in Staff Report EPW-17-004.

Body

 

RELEVANT POLICY:

 

Not applicable.

 

STRATEGIC RELEVANCE:

 

Resilient and Diverse Economy - Continue with remediation of proper and development of remediation plan.

 

Well Managed and Maintained Infrastructure - Identify infrastructure repair and proactively plan for replacement needs.

 

 

BACKGROUND:

 

The Township is in the process of redeveloping the Esquimalt Town Square (ETS) site. As part of this process, several pieces of infrastructure will need to be relocated or removed. This infrastructure includes:

 

                     Backup power generator

                     Fiber optic and copper communication infrastructure

                     Power transformer

                     Electric vehicle charging station

                     Relocation of monuments

                     Demolition of fire truck storage structure

                     Bike storage

                     Concrete blocks

                     Overhead lighting

                     Fencing

                     Playground equipment

                     Park furniture

                     Relocation of storm and sanitary service lines

 

This work will be divided into three projects. Each project will deal with a particular aspect of the relocation. The projects are:

 

Project 1 - Electrical Relocation

Ø                     Backup power generator

Ø                     Fiber optic and copper communication infrastructure

Ø                     Power transformer

Ø                     Electric vehicle charging station

Ø                     Fire truck storage structure demolition

 

Project 2 - Site features Relocation

Ø                     Relocation of monuments

Ø                     Bike storage

Ø                     Concrete blocks

Ø                     Playground equipment

Ø                     Park furniture

Ø                     Overhead lighting

Ø                     Fencing

 

Project 3 - Storm and Sanitary Relocation

Ø                     Storm service

Ø                     Sanitary service

 

Items such as trees, vegetation, irrigation lines, concrete features and asphalt surfaces will not be removed.

 

Projects 1 and 3 will have the work carried out by consultants and contractors with the Township acting as the Owner’s Representative. Project 2 will see the Township handling the majority of the work with assistance from contractors for any specialty work.

 

The status of each project is as follows:

 

Ø                     Project 1 - Project has been tendered and is awaiting award

Ø                     Project 2 - Scheduling of work has begun

Ø                     Project 3 - Request for Proposal is being prepared for the purpose of retaining a consultant

 

 

 

ISSUES: 

 

1.  Rationale for Selected Option

It is staff’s recommendation that Projects 1, 2, and 3 be given early budget approval within the 2017-2021 Financial Plan. Early approval is required as these projects are to commence over the next several months and will be completed prior to the final approval of the Financial Plan. The projects could be delayed until the Financial Plan is adopted but this will considerably impact the development of the site. These projects have to occur prior to the construction of the ETS parkade and structures.

 

2.  Organizational Implications

Projects 1 and 3 were incorporated into the Director of Engineering and Public Works’ work plan for 2016. Resources from Engineering and Public Works will be utilized as required to assist in the undertaking of Projects 1 and 3.

 

Project 2 will be the primary responsibility of Public Works and Parks with the majority of the work being carried out by Public Works. This work is scheduled to occur in the traditionally slower period for both departments and no significant operational impacts are expected on either department for the completion of this work.

 

The Chief Administrative Officer and other Directors (i.e. Parks and Recreation, Development, Finance) will also play a role in the completion of all three projects or dealing with the Developer. Their participation levels have been incorporated into their work plans with no significant operational impacts being expected due to the work.

 

3.  Financial Implications

The budget required for each project is as follows:

 

Project

Activity

Cost

Project 1 - Electrical

 

 

 

Construction

457,333

 

Contingency

21,667

 

Demolition of Fire Building

25,000

 

BC Hydro allowance

75,000

 

Total

579,000

 

The cost for the Consultant for this project was approved in 2016 from contingency funds for a total value of $100,000.

 

Project

Activity

Cost

Project 2 - Site Features

 

 

 

Construction

90,000

 

Contingency

10,000

 

Total

100,000

 

Project

Activity

Cost

Project 3 - Storm/Sanitary

 

 

 

Consultant

40,000

 

Construction

172,000

 

Total

212,000

 

A summary of the total cost for early approval is:

 

                     Project 1 = $579,000

                     Project 2 = $100,000

                     Project 3 = $212,000

                     Total =       $891,000

 

4.  Sustainability & Environmental Implications

 

Where possible and feasible, sustainability elements will be incorporated into the construction of each project. We will also strive to lower the environmental impact of each Project through methods of construction and disposal.

 

5.  Communication & Engagement

 

As contracts are awarded, the successful contractor will be contacted. The Township will issue updates to the Township’s website and other social media forums regarding the progress of the ETS project. Council will also receive periodic reports updating them on the progress of the ETS project as required.

 

ALTERNATIVES:

 

 

1.                     That Council gives early budget approval of Project 1 in the amount of $579,000, Project 2 in the amount of $100,000, and Project 3 in the amount of $212,000.

 

2.                     That Council does not give early budget approval of Project 1 in the amount of $579,000 and provides direction on the project.

 

3.                     That Council does not give early budget approval of Project 2 in the amount of $100,000 and provides direction on the project.

 

4.                     That Council does not give early budget approval of Project 3 in the amount of $212,000 and provides direction on the project.